Roads25IC0003

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - TACLOBAN-BAYBAY SOUTH RD - K0917 + 165 - K0917 + 430, BRGY. PAWING, PALO, LEYTE

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - TACLOBAN-BAYBAY SOUTH RD - K0917 + 165 - K0917 + 430, BRGY. PAWING, PALO, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱11,482,481.46. Status: Past target date (DPWH On-Going). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱99,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Cangumbang, Palo, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

245 projects · ₱18.1B total · 0 flags

4. Implementation

Contract Amount

₱11,482,481.46

Progress

Past target date (DPWH On-Going)

Start Date

February 24, 2025

Target End

April 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.