Buildings and Facilities19DK0120

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) LUAL BARRIO, MAUBAN, QUEZON

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) LUAL BARRIO, MAUBAN, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱2,970,000.00. Status: Reported complete (DPWH). Contractor on record: W J CONST OPC FORMERLY: W J CONST. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-B-19-0004171

₱46,809,683.00 · FY2019

Released to Jose R. Reyes Memorial Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

80 projects · ₱1.6B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS ATIMONAN-MAUBAN ROAD (MAUBAN SIDE) INCLUDING ROW AND SLOPE PROTECTION, MAUBAN, QUEZON

Quezon 1st DEO, Region IV-A

2018₱85.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - JCT MSR CALUMPANG - TAYABAS ROAD LEADING TO MINOR BASILICA OF ST. MICHAEL DE ARCHANGEL, AND KAMAY NI HEHESUS, TAYABAS, QUEZON

Quezon 1st DEO, Region IV-A

2022₱72.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM CONST OF BYPASS AND DIVERSION ROADPAGBILAO TAYABAS LUCBAN DIVERSION ROAD (LUCBAN SECTION) PACKAGE A, QUEZON, LUCBAN, QUEZON

Quezon 1st DEO, Region IV-A

2024₱72.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PAGBILAO-TAYABAS-LUCBAN DIVERSION ROAD (LUCBAN SECTION), QUEZON

Quezon 1st DEO, Region IV-A

2025₱60.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - LUCBAN DIVERSION ROAD, PACKAGE A, QUEZON

Quezon 1st DEO, Region IV-A

2022₱58.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS/NEW ROADS PAGBILAO-TAYABAS-LUCBAN DIVERSION ROAD (TAYABAS SIDE), PACKAGE B, QUEZON

Quezon 1st DEO, Region IV-A

2021₱57.9M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱2,970,000.00

Progress

Reported complete (DPWH)

Start Date

November 8, 2019

Target End

February 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.