Roads17K00156

ROAD UPGRADING (UNPAVED TO PAVED)BASED ON GRS,TB FOR UPGRADING TO PRS(HDM-4 PROJ. ANALYSIS)BONIFACIO

ROAD UPGRADING (UNPAVED TO PAVED)BASED ON GRS,TB FOR UPGRADING TO PRS(HDM-4 PROJ. ANALYSIS)BONIFACIO is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱95,887,136.98. Status: Reported complete (DPWH). Contractor on record: MINDANAO ROCK. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱95,887,136.98

Progress

Reported complete (DPWH)

Start Date

February 27, 2017

Target End

September 17, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.