Roads18BG0017

CONCRETING OF STO. TOMAS - DAGUPAN, STO. TOMAS, ALICIA, ISABELA, 0+000 - 0+783.00

CONCRETING OF STO. TOMAS - DAGUPAN, STO. TOMAS, ALICIA, ISABELA, 0+000 - 0+783.00 is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱4,701,751.11. Status: Reported complete (DPWH). Contractor on record: A DE GUIA CONST AND DEVELOPMENT CORP FORMERLY: A DE GUIA CONST. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

View all 112 projects →

4. Implementation

Contract Amount

₱4,701,751.11

Progress

Reported complete (DPWH)

Start Date

February 14, 2018

Target End

April 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.