Flood Control and Drainage18OE0025

ORGANIZATIONAL OUTCOME 2: PROTECH LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-BANK IMPROVEMENT (STEEL SHEET PILE), ESTERO DE SUNOG APOG, STA. 0+260.80 TO S

ORGANIZATIONAL OUTCOME 2: PROTECH LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-BANK IMPROVEMENT (STEEL SHEET PILE), ESTERO DE SUNOG APOG, STA. 0+260.80 TO S is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱48,973,913.26. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Bank Improvement (Steel Sheet Pile) Estero de Sunog Apog, Sta. 0+260.80 to Sta. 0+400.40, Brgy. 132 and Brgy. 137, Manila City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033895

₱0.00 · FY2018

Released to Dacap Norte National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

337 projects · ₱12.4B total · 0 flags

4. Implementation

Contract Amount

₱48,973,913.26

Progress

Reported complete (DPWH)

Start Date

February 14, 2018

Target End

August 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.