Flood Control and Drainage17OD0079

CONSTRUCTION OF FLOOD CONTROL WALL/RIPRAPPING ALONG THE BANKS OF VARIOUS CREEKS IN BRGY. 175, CALOOCAN CITY

CONSTRUCTION OF FLOOD CONTROL WALL/RIPRAPPING ALONG THE BANKS OF VARIOUS CREEKS IN BRGY. 175, CALOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱22,392,695.60. Status: Reported complete (DPWH). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST 2852. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 2852

145 projects · ₱8.8B total · 0 flags

4. Implementation

Contract Amount

₱22,392,695.60

Progress

Reported complete (DPWH)

Start Date

April 25, 2017

Target End

September 28, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.