Roads18EH0135

CONCRETING OF SITIO BAGOLAYAG FMR PHASE II, BGRY. TUBIGON, FERROL, ROMBLON

CONCRETING OF SITIO BAGOLAYAG FMR PHASE II, BGRY. TUBIGON, FERROL, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱4,802,566.71. Status: Reported complete (DPWH). Contractor on record: R G FLORENTINO CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,802,566.71

Progress

Reported complete (DPWH)

Start Date

November 22, 2018

Target End

January 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.