Roads18NB0070

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD IN SUPPORT OF MATCH FACTORY, TALACOGON, AGUSAN DEL SUR

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD IN SUPPORT OF MATCH FACTORY, TALACOGON, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱27,099,613.45. Status: Reported complete (DPWH). Contractor on record: DATREBIL CONST. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Dike along Poblacion-Magtuyon-Talacogon Road (Phase II) at Poblacion, San Luis, Agusan del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0003691

₱0.00 · FY2018

Released to Division of Agusan del Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

130 projects · ₱2.1B total · 0 flags

Other projects by this contractor

View all 130 projects →

4. Implementation

Contract Amount

₱27,099,613.45

Progress

Reported complete (DPWH)

Start Date

July 19, 2018

Target End

March 15, 2019

5. Audit