Construction of Flood Mitigation Structure24CL0127

Construction of Flood Control Structure along Bancal-San Isidro-Mambog River (Totun Lanum) Phase 3, Sitio Tambak, (North Side), Barangay Palanginan, Iba, Zambales

Construction of Flood Control Structure along Bancal-San Isidro-Mambog River (Totun Lanum) Phase 3, Sitio Tambak, (North Side), Barangay Palanginan, Iba, Zambales is a DPWH-tracked public work in IBA (CAPITAL) (ZAMBALES), ZAMBALES, Region III. Reported contract value: ₱47,579,211.86. Status: Reported complete (DPWH). Contractor on record: RAIK CONST AND DEVELOPMENT CORP FORMERLY: RAIK CONST AND SUPPLY. Figures trace to sumbong.

IBA (CAPITAL) (ZAMBALES), ZAMBALES, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bancal - San Isidro - Mambog River ( Totun Lanum ) Phase 1, Sitio Tambak, ( North Side ) , Barangay Palanginan, Iba, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0019786

₱28,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0004297

₱5,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007114

₱1,538,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007115

₱142,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,579,211.86

Progress

Reported complete (DPWH)

Start Date

February 22, 2024

Target End

November 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.