Flood Control and Drainage18CA0002

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL PROJECT IN COLO RIVER, MAITE SECTION, BARANGAY MAITEHERMOSA, BATAAN

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL PROJECT IN COLO RIVER, MAITE SECTION, BARANGAY MAITEHERMOSA, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱17,093,439.00. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱18,735,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project in Colo River, Maite Section, Brgy. Maite, Hermosa, Bataan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0014605

₱0.00 · FY2018

Released to Division of Bataan (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱17,093,439.00

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

July 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.