Roads20PK0036

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, LUBUAGAN-BATONG BUHAY-ABRA ROAD - K0462+177-K

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, LUBUAGAN-BATONG BUHAY-ABRA ROAD - K0462+177-K is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱25,236,233.25. Status: Reported complete (DPWH). Contractor on record: JTM CONST. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ag-Agama Creek Flood Control, Western uma, Lubuagan, Kalinga
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Upper Kalinga DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

114 projects · ₱4.3B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - NAMBARAN-ISABELA RD - K0509 + (-903) - K0520 + 865

Lower Kalinga DEO, Cordillera Administrative Region

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD) - K0490+848 - K0492+1025, K0492+1399.60 - K0494+458, K0499+097 - K0499+216.80

Region II, Region II

2025₱187.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - PEÑABLANCA-CALLAO CAVE ROAD (S05071LZ) - K0475 + 233 - K0483 + 550 & K0484 + 020 - K0486 + 434 (TWO LANES)

Cagayan 3rd DEO, Region II

2025₱144.6M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - KALINGA-CAGAYAN RD (CALANAN-ENRILE SECTION) - K0437 + (-055) - K0441 + 576, K0441 + 600 - K0444 + 214, K0444 + 315 - K0445 + 676

Cagayan 3rd DEO, Region II

2024₱144.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R. A. 11239 - PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG DAANG MAHARLIKA (CAGAYAN VALLEY RD) - K0484+855 - K0486+320, K0487+000 - K0487+484, K0487+610

Region II, Region II

2025₱132.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY ( CAGAYAN VALLEY ROAD) - K0471 + 128 - K0472 + 779.20

Region II, Region II

2025₱107.9M
Ongoing (DPWH-reported)
View all 114 projects →

4. Implementation

Contract Amount

₱25,236,233.25

Progress

Reported complete (DPWH)

Start Date

October 28, 2020

Target End

July 31, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.