Construction of Revetment22FD0011

Construction of Revetment, Sta. 3+713 to Sta. 3+800, Barangay Malubago, Sipocot, Camarines Sur

Construction of Revetment, Sta. 3+713 to Sta. 3+800, Barangay Malubago, Sipocot, Camarines Sur is a DPWH-tracked public work in SIPOCOT (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱29,699,598.42. Status: Reported complete (DPWH). Contractor on record: NFH CONST & SUPPLY. Figures trace to sumbong.

SIPOCOT (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Seawall) Barangay 1 to Barangay 4, Garchitorena, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002962

₱80,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

50 projects · ₱4.0B total · 5 flags

4. Implementation

Contract Amount

₱29,699,598.42

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

November 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.