Flood Control and Drainage21CF0154

CONSTRUCTION OF FLOOD CONTROL AND SLOPE PROTECTION ALONG RIVERSIDE OF BARANGAY CONCEPCION, RIO CHICO, PIAS TO MINALUNGAO, GENERAL TINIO, NUEVA ECIJA

CONSTRUCTION OF FLOOD CONTROL AND SLOPE PROTECTION ALONG RIVERSIDE OF BARANGAY CONCEPCION, RIO CHICO, PIAS TO MINALUNGAO, GENERAL TINIO, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱48,507,364.68. Status: Reported complete (DPWH). Contractor on record: E D LIBUNAO CONST. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control And Slope Protection Along Riverside of Barangay Concepcion, Rio Chico, Pias To Minalungao, General Tinio, Nueva Ecija
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Nueva Ecija 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,507,364.68

Progress

Reported complete (DPWH)

Start Date

August 13, 2021

Target End

March 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.