Roads15K00445

CONC. OF BRGY. BANGA NATL HIGHWAY MT. SPRING RESORT, WAO, LDS 1ST LD

CONC. OF BRGY. BANGA NATL HIGHWAY MT. SPRING RESORT, WAO, LDS 1ST LD is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱28,080,935.76. Status: Reported complete (DPWH). Contractor on record: M M A ACHIEVER CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,080,935.76

Progress

Reported complete (DPWH)

Start Date

March 7, 2016

Target End

June 29, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.