Bridges24JD0044

WIDENING OF PERMANENT BRIDGES, POLANDOC BRIDGE (B00523MN0 ALONG SINDANGAN-LILOY ROAD (PHASE II), LEON B. POSTIGO, ZAMBOANGA DEL NORTE

WIDENING OF PERMANENT BRIDGES, POLANDOC BRIDGE (B00523MN0 ALONG SINDANGAN-LILOY ROAD (PHASE II), LEON B. POSTIGO, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱81,204,750.00. Status: Past target date (DPWH On-Going). Contractor on record: ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP REVOKED 38958. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Talinga River ( Upstream ) , Talinga, Leon B. Postigo, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zamboanga del Norte 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 38958

57 projects · ₱5.3B total · 0 flags

Other projects by this contractor

View all 57 projects →

4. Implementation

Contract Amount

₱81,204,750.00

Progress

Past target date (DPWH On-Going)

Start Date

April 13, 2024

Target End

March 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.