Flood Control and Drainage22DN0065

REHABILITATION OF FLOOD CONTROL STRUCTURES, BULAO RIVER, ANTIPOLO CITY (FIRST DISTRICT)

REHABILITATION OF FLOOD CONTROL STRUCTURES, BULAO RIVER, ANTIPOLO CITY (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱93,122,484.15. Status: Reported complete (DPWH). Contractor on record: A J LAVA BUILDERS CORP FORMERLY: A J LAVA BUIL 22265. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱22,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Halang Creek to Muntindilaw River, Antipolo City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Rizal 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,122,484.15

Progress

Reported complete (DPWH)

Start Date

March 8, 2022

Target End

September 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.