Flood Control and Drainage22DN0031

REHABILITATION OF FLOOD CONTROL STRUCTURE, SUCABEN RIVER, PHASE 4, ANTIPOLO CITY (FIRST DISTRICT)

REHABILITATION OF FLOOD CONTROL STRUCTURE, SUCABEN RIVER, PHASE 4, ANTIPOLO CITY (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱93,122,456.64. Status: Past target date (DPWH On-Going). Contractor on record: A J LAVA BUILDERS CORP FORMERLY: A J LAVA BUIL 22265. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱22,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Halang Creek to Muntindilaw River, Antipolo City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Rizal 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,122,456.64

Progress

Past target date (DPWH On-Going)

Start Date

March 3, 2022

Target End

November 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.