Flood Control and Drainage20AB0030

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF THE LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT DONGDONG RIVER FLOOD CONTROL, BRGY. CARAY, NUEVA ERA, ILOCOS NORTE

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF THE LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT DONGDONG RIVER FLOOD CONTROL, BRGY. CARAY, NUEVA ERA, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱39,199,996.35. Status: Reported complete (DPWH). Contractor on record: ST TIMOTHY CONST CORP. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of the Laoag River Basin Flood Control and Sabo Project Dongdong River Flood Control, Brgy. Caray, Nueva Era, Ilocos Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

942 projects · ₱44.1B total · 42 flags

Other projects by this contractor

No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0578+640 - K0578+900 R/S

Region I, Region I

2023₱390.8M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 1), ORION, BATAA

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1

Region IV-B, Region IV-B

2022₱289.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
View all 942 projects →

4. Implementation

Contract Amount

₱39,199,996.35

Progress

Reported complete (DPWH)

Start Date

February 18, 2020

Target End

December 2, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.