Flood Control and Drainage21OA0044

CONST. OF 3 PS SACRISTIA ST., LUNA ST, PAEZ ST BRGY. SAN AGUSTIN, CONCEPCION MALABON CITY

CONST. OF 3 PS SACRISTIA ST., LUNA ST, PAEZ ST BRGY. SAN AGUSTIN, CONCEPCION MALABON CITY is a DPWH-tracked public work in Malabon-Navotas DEO, National Capital Region. Reported contract value: ₱57,460,714.84. Status: Reported complete (DPWH). Contractor on record: ROTAFLEX CONST AND DEVELOPMENT CORP FORMERLY:ROTA FLEX CONST. Figures trace to dpwh.

Malabon-Navotas DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱57,460,714.84

Progress

Reported complete (DPWH)

Start Date

April 19, 2021

Target End

December 14, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.