Roads22FF0039

BIP:ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD CONNECTING TO INDIGENEOUS PEOPLE(IP)COMMUNITIES,CONTINUATION OF ACCESS ROAD BRGY. BALONGAY TO BGRY. SAN BERNARDINO CALABANGA CAM. SUR

BIP:ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD CONNECTING TO INDIGENEOUS PEOPLE(IP)COMMUNITIES,CONTINUATION OF ACCESS ROAD BRGY. BALONGAY TO BGRY. SAN BERNARDINO CALABANGA CAM. SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱4,949,334.24. Status: Reported complete (DPWH). Contractor on record: PEU CONST AND SUPPLY. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation/Improvement of Flood Mitigation Structure, Calabanga Flood Control, Brgy. Sabang-Salvacion Baybay- San Roque-San Pablo, Calabanga, Camarines Sur (Both Sides)
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camarines Sur 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

12 projects · ₱305.2M total · 0 flags

Other projects by this contractor

No sat.

OO1: ASSET PRESERVATION PROGRAM- REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- SECONDARY ROADS-PILI DIVERSION ROAD-K0450+000-K0450+876.30, K0451+125.30-K0451+465.20, K0451+528-K0452+245, PILI, CAMARINES SUR

Camarines Sur 3rd DEO, Region V

2023₱85.6M
Reported complete (DPWH)
No sat.

BIP;ACCESS ROAD &/OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONST, OF PALESTINA-YABU- CAROLINA ROAD, PILI CAMARINES SUR

Camarines Sur 3rd DEO, Region V

2023₱75.9M
Reported complete (DPWH)
No sat.

001;NETWORK DEVELOPMENT PROG.-ROAD WIDENING-TERTIARY ROADS-NAGA CAROLINA-PANICUASON RD.-KO442+371-KO442+787 NAGA CITY CAMARINES SUR

Camarines Sur 3rd DEO, Region V

2024₱39.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)-CONSTRUCTION OF CIRCUMFERENTIAL ROAD NETWORK (TRAINING GRO

Region V, Region V

2024₱23.4M
Past target date (DPWH On-Going)
No sat.

001;NETWORK DEVELOPMENT PROG.-CONST OF BY PASS ROAD & DIVERSION ROADS-REHAB, OF MAGSAYSAY AVENUE- BALATAS- CARARAYAN- MAHARLIKA(DEL ROSARIO) BY PASS ROAD NAGA CITY CAMARINES SUR(PHASE IV) NAGA CITY CAMARINES SUR

Camarines Sur 3rd DEO, Region V

2023₱19.1M
Reported complete (DPWH)
No sat.

001;NETWORK DEVELOPMENT PROGRAM-CONST OF BY PASS & DIVERSION ROADS JCT.-ALONG- DM DEL ROSARIO- CARARAYAN-SAN ISIDRO NRJ CAROLINA BY PASS ROAD IN NAGA CITY CAM. SUR

Camarines Sur 3rd DEO, Region V

2023₱19.1M
Past target date (DPWH On-Going)
View all 12 projects →

4. Implementation

Contract Amount

₱4,949,334.24

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

July 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.