Roads21CL0085

CONSTRUCTION OF MISSING LINKS/NEW ROADS STA.CRUZ- MANGATAREM ROAD (ZAMBALES SIDE, PHASE 7) STA. CRUZ, ZAMBALES

CONSTRUCTION OF MISSING LINKS/NEW ROADS STA.CRUZ- MANGATAREM ROAD (ZAMBALES SIDE, PHASE 7) STA. CRUZ, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱65,169,549.89. Status: Reported complete (DPWH). Contractor on record: EDFROBON CONST SERVICES INC 36761. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,118,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Flood Control Facilities at Tambak River Phase 3, Upstream, Sta. 0+869 - Sta. 1+199, Iba, Zambales
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Zambales 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 36761

17 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM-NATIONAL BLDG. PROGRAM-BLDGS, & OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONST. OF BLDS. FOR VIROLOGY INSTITUTE OF SCIENCE AND TECHNOLOGY OF THE PHILS. (VIP), NEW CLARK CITY, CLARK FREEPORT & SPL. ECONOMIC ZONE (CFEZ), CAPAS, TARLAC

Region III, Region III

2023₱236.5M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BLDG. PROGRAM-BLDGS. & OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONST. OF BLDG. FOR VIROLOGY INSTITUTE OF SCIENCE AND TECH. OF THE PHILIPPINES (VIP), NEW CLARK CITY, CLARK FREEPORT AND SPECIAL ECONOMIC ZONE (CFEZ), CAPAS, TARLAC.

Region III, Region III

2022₱142.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY-CONST. OF ARMY LEADERSHIP DEV'T. & EDUCATION CENTER (ALDEC) PHASE I-TRADOC MPB, TRADOC, PA, CAMP O'DONNEL, CAPAS, TARLAC, PROV. OF TARLAC

Region III, Region III

2020₱117.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION)-PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2022₱99.4M
Reported complete (DPWH)

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN MIGUEL RIVER, BARANGAY SAN JUAN, SAN MIGUEL, BULACAN, PACKAGE I

Region III, Region III

2024₱96.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-NATIONAL BLDG. PROGRAM-BLDGS. & OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-STRUCTURAL IMPR'VT OF PUBLIC BLDGS. & CONST. OF EVACUATION CENTERS-CONST. OF EVACUATION CENTERS IN DINALUNGAN, AURORA; HERMOSA, BATAAN & SAN MARCELINO, ZAMBALES.

Region III, Region III

2022₱96.5M
Reported complete (DPWH)
View all 17 projects →

4. Implementation

Contract Amount

₱65,169,549.89

Progress

Reported complete (DPWH)

Start Date

September 24, 2021

Target End

June 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.