Roads19ED0009

ROAD WIDENING ALONG CALAPAN SOUTH ROAD K0034+123 - K0034+1028, K0035+399 - K0035+671, K0036+885 - K0037+221, K0039+498 - K0039+645, K0040+566 - K0040+932, K0040+995 - K0041+252, K0041+486 - K0042+054, K0043+536 - K0043+592, VICTORIA - SOCORRO, ORIENTAL MI

ROAD WIDENING ALONG CALAPAN SOUTH ROAD K0034+123 - K0034+1028, K0035+399 - K0035+671, K0036+885 - K0037+221, K0039+498 - K0039+645, K0040+566 - K0040+932, K0040+995 - K0041+252, K0041+486 - K0042+054, K0043+536 - K0043+592, VICTORIA - SOCORRO, ORIENTAL MI is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱81,636,033.45. Status: Reported complete (DPWH). Contractor on record: SANLAHI GROUP OF BUILDERS INC. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0000617

₱1,331,464,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

32 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱81,636,033.45

Progress

Reported complete (DPWH)

Start Date

July 25, 2019

Target End

September 11, 2020

5. Audit