Buildings and Facilities21M00135

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TINUNGKAAN, NORTH UPI, MAGUINDANAO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TINUNGKAAN, NORTH UPI, MAGUINDANAO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱2,478,883.70. Status: Reported complete (DPWH). Contractor on record: BAMEC DEVELOPERS. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,478,883.70

Progress

Reported complete (DPWH)

Start Date

December 28, 2021

Target End

April 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.