Roads22E00074

REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIED - SECONDARY ROADS - MINDORO WEST COASTAL ROAD K0447+300 - K0447+360; K0447+400 - K0447+450.82, OCCIDENTAL MINDORO

REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIED - SECONDARY ROADS - MINDORO WEST COASTAL ROAD K0447+300 - K0447+360; K0447+400 - K0447+450.82, OCCIDENTAL MINDORO is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱86,849,997.70. Status: Reported complete (DPWH). Contractor on record: NEWINGTON BUILDERS INC FOR: E GARDIOLA CONSTRUC. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

189 projects · ₱20.4B total · 0 flags

4. Implementation

Contract Amount

₱86,849,997.70

Progress

Reported complete (DPWH)

Start Date

July 6, 2022

Target End

December 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.