Buildings and Facilities17FO0196

CLUSTER XXXI-2017: CONSTRUCTION OF 3 UNITS, 1-STOREY SCHOOL BUILDINGS IN POLANGUI (C)

CLUSTER XXXI-2017: CONSTRUCTION OF 3 UNITS, 1-STOREY SCHOOL BUILDINGS IN POLANGUI (C) is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱10,553,100.42. Status: Reported complete (DPWH). Contractor on record: 4DOVE BUILDERS CORP 36232. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 36232

53 projects · ₱708.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF CABILOGAN RIVER FLOOD MITIGATION STRUCTURE, BARANGAY B

Albay 3rd DEO, Region V

2024₱112.3M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SAN VICENTE-OBALIW RIÑAS ROAD, OAS, ALBAY

Albay 3rd DEO, Region V

2023₱49.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF MAHABA-BUSAY ROAD IN LIGA

Albay 3rd DEO, Region V

2024₱47.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF DUNAO-BONGA-PAULOG ROAD

Albay 3rd DEO, Region V

2024₱40.0M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BRGY. BINATAGAN FMR, BRGY. BINATAGAN, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2024₱29.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF TINAGO/MAHABA BUSAY ROAD (PHASE 2), BARANGAY MAHABA TO BARANGAY BUSAY, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2022₱25.7M
Past target date (DPWH On-Going)
View all 53 projects →

4. Implementation

Contract Amount

₱10,553,100.42

Progress

Reported complete (DPWH)

Start Date

January 19, 2018

Target End

April 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.