Rehabilitation / Major Repair of Flood Control Structure23CD0046

Rehabilitation of Flood Control Wall along Meycauayan River, Barangay Tawiran to Wawang Pulo (Section II), Obando Section, Obando, Bulacan

Rehabilitation of Flood Control Wall along Meycauayan River, Barangay Tawiran to Wawang Pulo (Section II), Obando Section, Obando, Bulacan is a DPWH-tracked public work in OBANDO (BULACAN), BULACAN, Region III. Reported contract value: ₱46,058,208.67. Status: Reported complete (DPWH). Contractor on record: JB CONST AND SUPPLY INC FORMERLY:JB CONST AND SUPPLY. Figures trace to sumbong.

OBANDO (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Wall along Meycauayan River, Barangay Tawiran to Wawang Pulo (Section II), Obando Section, Obando, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

74 projects · ₱3.5B total · 2 flags

4. Implementation

Contract Amount

₱46,058,208.67

Progress

Reported complete (DPWH)

Start Date

March 13, 2023

Target End

August 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.