Construction of Flood Mitigation Structure22CN0114

Construction of Flood Control Structure, Brgy. Salay, Dipaculao, Aurora

Construction of Flood Control Structure, Brgy. Salay, Dipaculao, Aurora is a DPWH-tracked public work in DIPACULAO (AURORA), AURORA, Region III. Reported contract value: ₱34,300,000.00. Status: Reported complete (DPWH). Contractor on record: ALEXI LOUISSE CONST & GEN MERCHANDISE. Figures trace to sumbong.

DIPACULAO (AURORA), AURORA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Salay, Dipaculao, Aurora
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002891

₱787,770,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001729

₱22,200,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001625

₱20,500,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱687.5M total · 5 flags

4. Implementation

Contract Amount

₱34,300,000.00

Progress

Reported complete (DPWH)

Start Date

March 14, 2022

Target End

June 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.