Roads24KA0070

ROAD WIDENING ALONG KAPALONG-TALAINGOD-VALENCIA (BUKIDNON) RD- K1543 + 000 - K1544 + 506SAN FERNANDO, BUKIDNON 2ND LD

ROAD WIDENING ALONG KAPALONG-TALAINGOD-VALENCIA (BUKIDNON) RD- K1543 + 000 - K1544 + 506SAN FERNANDO, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱75,986,030.00. Status: Past target date (DPWH On-Going). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Sinanglanan, Malaybalay City, Bukidnon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bukidnon 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱75,986,030.00

Progress

Past target date (DPWH On-Going)

Start Date

April 25, 2024

Target End

May 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.