Flood Control and Drainage20PA0080

CONSTRUCTION OF GABION TYPE FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BANK WITHIN THE VICINITY OF BRGY. STA. ROSA, BANGUED, ABRA

CONSTRUCTION OF GABION TYPE FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BANK WITHIN THE VICINITY OF BRGY. STA. ROSA, BANGUED, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱19,797,190.00. Status: Reported complete (DPWH). Contractor on record: R A FANGLAYAN RAF GEN CONST INC FORMERLY:RAF GEN CONST. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gabion type flood control structure along Abra River bank within the vicinity of Brgy. Sta. Rosa, Bangued, Abra
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Abra DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

211 projects · ₱3.0B total · 0 flags

4. Implementation

Contract Amount

₱19,797,190.00

Progress

Reported complete (DPWH)

Start Date

November 23, 2020

Target End

May 11, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.