Roads23DF0183

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMROAD WIDENING - TERTIARY ROADSLABANAN SA BINAKAYAN DIV RD - K0022 + 449 - K0022 + 846

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMROAD WIDENING - TERTIARY ROADSLABANAN SA BINAKAYAN DIV RD - K0022 + 449 - K0022 + 846 is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱16,201,214.39. Status: Reported complete (DPWH). Contractor on record: N LIM DY CONST 32897. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System in Barangay Binakayan (Covelandia Road and Tirona Highway), Kawit, Cavite
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cavite 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 32897

15 projects · ₱531.5M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MALIMANGO RIVER, BRGY. LIGTONG 4, PHASE I

Cavite 1st DEO, Region IV-A

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS CONST OF REVETMENT ALONG SAN JUAN RIVER, PHASE 3, BRGY MARULAS, KAWIT, CAVITE

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAMMULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI PURPOSE BUILDING IN BRGY. BINAKAYAN, KAWIT, CAVITE (PHASE 2) - COMPLETION OF PUBLIC MARKET

Cavite 1st DEO, Region IV-A

2023₱79.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE FACILITY (PHASE 1), BINAKAYAN, KAWIT, CAVITE

Cavite 1st DEO, Region IV-A

2022₱69.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (NOVELETA MUNICIPAL HALL), NOVELETA, CAVITE

Cavite 1st DEO, Region IV-A

2024₱35.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT), BARANGAY ANIBAN 1 (FORMERLY ANIBAN 1, 3 AND 5), BACOOR CITY, CAVITE

Cavite 3rd DEO, Region IV-A

2024₱29.4M
Past target date (DPWH On-Going)
View all 15 projects →

4. Implementation

Contract Amount

₱16,201,214.39

Progress

Reported complete (DPWH)

Start Date

September 6, 2023

Target End

February 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.