GAA 2018 OO-118DD0252

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT, OFF- CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS, LIPA- BALETE RD (K0079 + 725.00 TO K0080 + 583.00; K0080 + 796.00 TO K0081 + 930.00)

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT, OFF- CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS, LIPA- BALETE RD (K0079 + 725.00 TO K0080 + 583.00; K0080 + 796.00 TO K0081 + 930.00) is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱66,943,693.51. Status: Reported complete (DPWH). Contractor on record: JASMIG CONST CORP FORMERLY: JASMIG CONST SUPPLY. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Drainage System, Brgy. Bigain 2, San Jose, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

373 projects · ₱15.3B total · 0 flags

4. Implementation

Contract Amount

₱66,943,693.51

Progress

Reported complete (DPWH)

Start Date

May 28, 2018

Target End

March 24, 2019

5. Audit