CONCRETING OF SITIO WALA, BRGY. STO. DOMINGO FMR PHASE 2, BRGY. STO. DOMINGO, VINZONS, CAMARINES NORTE, VINZONS, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱11,939,984.64. Status: Reported complete (DPWH). Contractor on record: 888RV CONST AND SUPPLIES. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

113 projects · ₱811.7M total · 0 flags

4. Implementation

Contract Amount

₱11,939,984.64

Progress

Reported complete (DPWH)

Start Date

September 29, 2023

Target End

January 30, 2024