Flood Control and Drainage21FN0024

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BARIT RIVER, DOWNSTREAM OF MALIBAN BRIDGE, SAN ESTEBAN· STA. BARBARA SECTION, NABUA, CAMARINES SUR

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BARIT RIVER, DOWNSTREAM OF MALIBAN BRIDGE, SAN ESTEBAN· STA. BARBARA SECTION, NABUA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱35,379,913.43. Status: Reported complete (DPWH). Contractor on record: E A SANCHO CONST INC FORM E A SANCHO CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/ Rehabilitation of Flood Control Structure along Barit River, Downstream of Maliban Bridge, San Esteban-Sta. Barbara Section, Nabua, Camarines Sur
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Camarines Sur 5th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

113 projects · ₱3.8B total · 0 flags

Other projects by this contractor

View all 113 projects →

4. Implementation

Contract Amount

₱35,379,913.43

Progress

Reported complete (DPWH)

Start Date

February 19, 2021

Target End

August 23, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.