Roads21K00354

PREVENTIVE MAINTENANCE-PRIMARY ROAD, SAYRE HIGHWAY - K1490+970-K1491+027, K1491+056-K1491+175

PREVENTIVE MAINTENANCE-PRIMARY ROAD, SAYRE HIGHWAY - K1490+970-K1491+027, K1491+056-K1491+175 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱6,203,672.61. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱6,203,672.61

Progress

Reported complete (DPWH)

Start Date

October 29, 2021

Target End

December 11, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.