Buildings and Facilities24KJ0118

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY LORENZO TAN, TANGUB CITY, MISAMIS OCCIDENTAL

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY LORENZO TAN, TANGUB CITY, MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱1,920,599.27. Status: Reported complete (DPWH). Contractor on record: WEISENWORK CONST. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Aloran River, Aloran, Misamis Occidental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Misamis Occidental 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

97 projects · ₱1.9B total · 0 flags

Other projects by this contractor

View all 97 projects →

4. Implementation

Contract Amount

₱1,920,599.27

Progress

Reported complete (DPWH)

Start Date

August 5, 2024

Target End

October 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.