CONSTRUCTION OF MULTI-PURPOSE FACILITY INCLUDING SITE DEVELOPMENT, FISH PORT COMPLEX, PHASE 1, MATI CITY, DAVAO ORIENTAL

CONSTRUCTION OF MULTI-PURPOSE FACILITY INCLUDING SITE DEVELOPMENT, FISH PORT COMPLEX, PHASE 1, MATI CITY, DAVAO ORIENTAL is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱143,302,373.69. Status: Past target date (DPWH On-Going). Contractor on record: METRO GEAR CONST CORP. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱143,302,373.69

Progress

Past target date (DPWH On-Going)

Start Date

August 14, 2023

Target End

July 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.