Roads23PL0045

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - LUCOG-MAGNAO ROAD CONNECTING MT. PROVINCE BOUNDARY-CALANAN-ABBUT NATIONAL ROAD

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - LUCOG-MAGNAO ROAD CONNECTING MT. PROVINCE BOUNDARY-CALANAN-ABBUT NATIONAL ROAD is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱3,910,011.34. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: IITYA CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of the Flood Control Structure at Brgy. Cabaruan, Tabuk City, Kalinga Province
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Lower Kalinga DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

9 projects · ₱60.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - LUCOG-MAGNAO ROAD CONNECTING MT. PROV

Lower Kalinga DEO, Cordillera Administrative Region

2024₱14.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - LUCOG-MAGNAO ROAD CONNECTING

Lower Kalinga DEO, Cordillera Administrative Region

2025₱9.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - IMPROVEMENT OF ACCESS ROAD IN BARANGAYS LACNOG (SITIO DANANAO), CABARUAN

Lower Kalinga DEO, Cordillera Administrative Region

2023₱8.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MT. PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT ROAD (CAGALUAN-CALANAN SETION) - K0470+(-003) - K

Lower Kalinga DEO, Cordillera Administrative Region

2023₱6.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BULANAO CREEK, SAN JUAN AND PUROK 3-4, TUGA, TAB

Lower Kalinga DEO, Cordillera Administrative Region

2025₱4.8M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MATALIBONG (PHASE 2), LOWER UMA,

Upper Kalinga DEO, Cordillera Administrative Region

2025₱4.8M
Reported complete (100% progress, DPWH status On-Going)
View all 9 projects →

4. Implementation

Contract Amount

₱3,910,011.34

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 4, 2023

Target End

July 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.