CONCRETING OF BRGY. TALAMPAS TO BRGY. CAMBAOG FMR, BRGY. TALAMPAS AND BRGY. CAMBAOG, BUSTOS, BULACAN

CONCRETING OF BRGY. TALAMPAS TO BRGY. CAMBAOG FMR, BRGY. TALAMPAS AND BRGY. CAMBAOG, BUSTOS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱19,302,303.46. Status: Reported complete (DPWH). Contractor on record: C. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Brgy. Balungao, Calumpit, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

231 projects · ₱6.0B total · 0 flags

4. Implementation

Contract Amount

₱19,302,303.46

Progress

Reported complete (DPWH)

Start Date

April 6, 2021

Target End

November 1, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.