Flood Control and Drainage19I00088

CONSTRUCTION (COMPLETION) OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, SUBSECTION 4.1B, STA. 1+180.00 - STA. 2+360.00, TACLOBAN CITY, LEYTE

CONSTRUCTION (COMPLETION) OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, SUBSECTION 4.1B, STA. 1+180.00 - STA. 2+360.00, TACLOBAN CITY, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱108,078,698.79. Status: Reported complete (DPWH). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

245 projects · ₱18.1B total · 0 flags

4. Implementation

Contract Amount

₱108,078,698.79

Progress

Reported complete (DPWH)

Start Date

July 31, 2019

Target End

May 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.