GAA 2024 OO-124PB0013

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0613 + 012 - K0613 + 300

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0613 + 012 - K0613 + 300 is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱14,291,608.03. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ISAGA BUILDERS. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Barren River ( Downstream ) Flood Control Structure along Chico River Basin, Sta. 37 + 200 - Sta. 38 + 973
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Apayao 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱142.6M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BARREN RIVER (UPSTREAM) FLOOD CONTROL, BRGY. TALIFUGO, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2020₱19.0M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0609+175 - K0609+206, K0611+015 - K0611+036, K0611+335 - K0611+359

Apayao 1st DEO, Cordillera Administrative Region

2023₱16.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0623 + 742 - K0623 + 962

Apayao 1st DEO, Cordillera Administrative Region

2024₱14.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, ABBUT-CONNER RD - K0553+041 - K0553+366, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2022₱9.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, CONNER-KABUGAO RD - K0591 + 580 - K0591 + 620

Apayao 1st DEO, Cordillera Administrative Region

2024₱9.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- OFF-CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS, ABBUT-CONNER RD- K0548+796-K0549+140

Apayao 1st DEO, Cordillera Administrative Region

2024₱8.2M
Reported complete (100% progress, DPWH status On-Going)
View all 22 projects →

4. Implementation

Contract Amount

₱14,291,608.03

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 11, 2024

Target End

July 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.