Roads22PF0032

OFF-CARRIAGE IMPROVEMENT - SECONDARY ROADS: CONG. ANDRES ACOP COSALAN RD. K0365+000 - K0365+679

OFF-CARRIAGE IMPROVEMENT - SECONDARY ROADS: CONG. ANDRES ACOP COSALAN RD. K0365+000 - K0365+679 is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱14,700,000.00. Status: Reported complete (DPWH). Contractor on record: GELLE CONST SERVICES. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Ambalideng Flood Control, Ambalideng, Poblacion, Kibungan, Benguet
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Benguet 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22PF0032OFF-CARRIAGE IMPROVEMENT ACOP COSALAN RD.

₱14,649,673.70 · GELLE CONSTRUCTION SERVICES

Contractor

12 projects · ₱121.9M total · 0 flags

Other projects by this contractor

No sat.

OO1-REHAB/RECONSTN OF RDS W/ SLIPS, SLOPE COLLAPSE & LANDSLIDE-BAGUIO-BONTOC RD K0347+000-K0347+263

Mountain Province 1st DEO, Cordillera Administrative Region

2023₱23.4M
Reported complete (DPWH)
No sat.

Construction of Flood Mitigation Structure along Agno River, Salingao Section, Sta. 0+022 - Sta. 0+306 (B.S), Buguias, Benguet

BUGUIAS (BENGUET), BENGUET, Cordillera Administrative Region

2024₱19.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD-K0463+667-K0463+1152

Mountain Province 2nd DEO, Cordillera Administrative Region

2024₱15.4M
Reported complete (DPWH)
No sat.

CONCRETING OF SITIO BANSA TO SITIO MOSGO, BRGY. MONAMON NORTE FMR, BRGY. MONAMON NORTE, BAUKO, MT. PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2022₱11.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD-K0440+1002-K0441+041

Mountain Province 2nd DEO, Cordillera Administrative Region

2024₱10.4M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROAD: KIANGAN-TINOC-BUGUIAS RD - K0360+614 - K0360+700, K0363+625 - K0363+665, K0363+775 - K0363+882

Benguet 2nd DEO, Cordillera Administrative Region

2024₱7.5M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱14,700,000.00

Progress

Reported complete (DPWH)

Start Date

June 1, 2022

Target End

November 12, 2022

5. Audit