GAA 2025 OO-225BC0014

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTUR

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTUR is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱96,349,818.22. Status: Reported complete (DPWH). Contractor on record: JC PALOMO CONST. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Alannay Flood Control Structure along Zinundungan River, Lasam, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cagayan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

95 projects · ₱2.5B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG-LINAO-ATULUYANBAGAY-BUNTUN), PACKAGE 1, CAGAYAN

Region II, Region II

2024₱149.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING LINKS/NEW ROADS: SAN JOSE-QUIBAL ROAD, PACKAGE 1, CAGAYAN

Region II, Region II

2022₱115.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS -TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG - LINAO - ATULAYAN - BAGAY - BUNTUN), PACKAGE 1, CAGAYAN

Region II, Region II

2023₱106.1M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS -TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG - LINAO - ATULAYAN - BAGAY - BUNTUN), PACKAGE 3, CAGAYAN

Region II, Region II

2023₱100.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING LINKS/NEW ROADS: SAN JOSE-QUIBAL ROAD, PACKAGE 2, CAGAYAN

Region II, Region II

2022₱100.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - SAMPAGUITA-WARAT-LA SUERTE-CATARAUAN-AFUSING RD PHASE III

Cagayan 3rd DEO, Region II

2024₱96.4M
Past target date (DPWH On-Going)
View all 95 projects →

4. Implementation

Contract Amount

₱96,349,818.22

Progress

Reported complete (DPWH)

Start Date

February 21, 2025

Target End

October 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.