Construction of Flood Mitigation Structure24EI0079

Construction of Cavillan River Waterway Enhancement Structure (Nasukob Section), along Sitio Cavillan, Barangay Nasukob, Bulalacao, Oriental Mindoro

Construction of Cavillan River Waterway Enhancement Structure (Nasukob Section), along Sitio Cavillan, Barangay Nasukob, Bulalacao, Oriental Mindoro is a DPWH-tracked public work in BULALACAO (SAN PEDRO) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱29,397,112.52. Status: Reported complete (DPWH). Contractor on record: D M MALIWANAG BUILDERS AND ENT. Figures trace to sumbong.

BULALACAO (SAN PEDRO) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canturing River Flood Control, Brgy. Nasaug, Segment 2, Maasin City, Southern Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0020130

₱20,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0006527

₱5,615,052.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008383

₱1,386,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004004

₱564,186.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0002609

₱25,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004024

₱237,954.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004305

₱193,512.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008398

₱128,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0006528

₱521,819.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱29,397,112.52

Progress

Reported complete (DPWH)

Start Date

April 3, 2024

Target End

October 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.