Water Provision and Storage24GB0100

CONSTRUCTION (EXPANSION) OF WATER SUPPLY SYSTEM AT BRGY. ILAYA AND PIPELINE EXTENSION TO BRGY. IGBA

CONSTRUCTION (EXPANSION) OF WATER SUPPLY SYSTEM AT BRGY. ILAYA AND PIPELINE EXTENSION TO BRGY. IGBA is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱3,911,375.32. Status: Reported complete (DPWH). Contractor on record: N D M CONST SERVICES. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Sibalom River, Brgy. Maragubdub, San Remigio, Antique
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Antique DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱3,911,375.32

Progress

Reported complete (DPWH)

Start Date

April 5, 2024

Target End

June 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.