Buildings and Facilities17DJ0067

CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOMS ACADEMIC SCHOOL BUILDING AT DAGATAN NATIONAL HIGH SCHOOL, DOLORES, QUEZON

CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOMS ACADEMIC SCHOOL BUILDING AT DAGATAN NATIONAL HIGH SCHOOL, DOLORES, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱32,269,430.46. Status: Reported complete (DPWH). Contractor on record: M G VILLAMIN CONST. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱32,269,430.46

Progress

Reported complete (DPWH)

Start Date

November 24, 2017

Target End

August 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.