Buildings and Facilities19DM0098

CONSTRUCTION OF TWO(2)-STOREY SIX(6)-CLASSROOM SCHOOL BUILDING AT DULONG BAYAN ES, PITOGO, QUEZON

CONSTRUCTION OF TWO(2)-STOREY SIX(6)-CLASSROOM SCHOOL BUILDING AT DULONG BAYAN ES, PITOGO, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱16,999,988.64. Status: Reported complete (DPWH). Contractor on record: M G VILLAMIN CONST. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱16,999,988.64

Progress

Reported complete (DPWH)

Start Date

August 20, 2019

Target End

June 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.