Roads18GE0081

ROAD WIDENING-GUIMARAS CIRCUMFERENTIAL RD INCL. ROW-K0006+600-K0006+789, K0007+151-K0007+237, K0007+354-K0008+000

ROAD WIDENING-GUIMARAS CIRCUMFERENTIAL RD INCL. ROW-K0006+600-K0006+789, K0007+151-K0007+237, K0007+354-K0008+000 is a DPWH-tracked public work in Guimaras DEO, Region VI. Reported contract value: ₱37,516,968.71. Status: Reported complete (DPWH). Contractor on record: S T SALCEDO CONST CORP FORMERLY: SHAK CONST. Figures trace to dpwh.

Guimaras DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Nagay River along Guimaras Circumferential Road, Nagay, San Lorenzo, Guimaras
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-18-0013467

₱0.00 · FY2018

Released to Division of Guimaras (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱37,516,968.71

Progress

Reported complete (DPWH)

Start Date

June 9, 2018

Target End

January 4, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.