Buildings and Facilities18IF0151

CY 2018 BASIC EDUCATIONAL FACILITIES FUND (BEFF), CONSTRUCTION OF CLASSROOMS, BATCH 3, L. CABAHUG ELEMENTARY SCHOOL, ORMOC CITY

CY 2018 BASIC EDUCATIONAL FACILITIES FUND (BEFF), CONSTRUCTION OF CLASSROOMS, BATCH 3, L. CABAHUG ELEMENTARY SCHOOL, ORMOC CITY is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱3,755,498.53. Status: Reported complete (DPWH). Contractor on record: JA ACHACOSO ENT. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Ahag, Ormoc City, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0003815

₱482,159.00 · FY2018

Released to Division of Southern (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

132 projects · ₱3.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION OF THE REGIONAL CULTURAL HUB, PHASE I, TAGBILARAN CITY, BOHOL PROVINCE

Region VII, Region VII

2021₱135.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE, PACKAGE 2, BARANGAY STO NIÑO - BARANGAY MINDANAO, MALABU

Cebu 7th DEO, Region VII

2025₱97.5M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING PALOMPON - ISABEL - MERIDA - ORMOC ROAD K1098+000 - K1101+416

Leyte 4th DEO, Region VIII

2018₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) - AS PER R.A. 11239, CONSTRUCTION AND INSTALLATION OF SOLAR STREETLIGHTS, SAFETY SIGNS AND DEVICES - K0065+000 - K0072+000, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2021₱96.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SHORELINE PROTECTION STRUCTURES - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. (S00228LT) - ALONG ST. BERNARD SECTION, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱89.8M
Past target date (DPWH On-Going)

CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. - (S00228LT) ALONG SAN JUAN SECTION, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱85.6M
Reported complete (100% progress, DPWH status On-Going)
View all 132 projects →

4. Implementation

Contract Amount

₱3,755,498.53

Progress

Reported complete (DPWH)

Start Date

December 10, 2018

Target End

March 4, 2019

5. Audit