Buildings and Facilities25O00108

CONSTRUCTION OF SAF HEADQUARTERS BUILDING (PNP-SAF GYM), CAMP BAGONG DIWA, TAGUIG (PHASE 5)

CONSTRUCTION OF SAF HEADQUARTERS BUILDING (PNP-SAF GYM), CAMP BAGONG DIWA, TAGUIG (PHASE 5) is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱28,327,660.18. Status: Past target date (DPWH On-Going). Contractor on record: TWENTYSIX CONST INC. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,327,660.18

Progress

Past target date (DPWH On-Going)

Start Date

July 18, 2025

Target End

January 13, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.