Flood Control and Drainage25AA0166

FLOOD MANAGEMENT PROGRAM - CONST/REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST OF FLOOD CONTROL STRUCTURE ALONG LAOAG RIVER BASIN AND TRIBUTARIES, UPSTREAM OF CAVIT BRIDGE, BARANGAY CAVIT, LAOAG CITY, I.N.

FLOOD MANAGEMENT PROGRAM - CONST/REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST OF FLOOD CONTROL STRUCTURE ALONG LAOAG RIVER BASIN AND TRIBUTARIES, UPSTREAM OF CAVIT BRIDGE, BARANGAY CAVIT, LAOAG CITY, I.N. is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱47,051,430.84. Status: Past target date (DPWH On-Going). Contractor on record: ROTAFLEX CONST AND DEVELOPMENT CORP FORMERLY:ROTA FLEX CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Laoag River Basin and Tributaries, Upstream of Cavit Bridge, Barangay Cavit, Laoag City, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

77 projects · ₱2.8B total · 6 flags

4. Implementation

Contract Amount

₱47,051,430.84

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

September 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.